Zeta Test Management Online documentation

Performing test runs

After you have filled a test plan with all desired test units and test cases, one or multiple testing users can perform test runs.

To start a new test run, follow these steps:

  1. Select the test plan in the structure view of the main window.
  2. Right-click the test plan.
  3. Select "Start new test run" from the context menu. →The dialog window "Start test run" opens.
  4. Select the elements to test.
  5. Confirm with "OK". → The test run will be created. → The dialog window "Perform tests" will open.
  6. Perform the tests and enter the results.
  7. Click on the "Next" button to navigate to the next test.
  8. If you have performed all tests or want to pause the test prematurely, click on the "Close" button.

You can continue a test you have paused at any time.

To continue a non-closed test run, follow these steps:

  1. Select the test run in the structure view of the main window.
  2. Right click the test run.
  3. Select "Continue tests" from the context menu. → The dialog window "Perform tests" will open.
  4. Perform the tests and enter the results.
  5. Click on the "Next" button to navigate to the next test.
  6. If you have performed all tests or want to pause the test prematurely, click on the "Close" button.

Please note:
The dialog window for performing tests is non-modal, i.e. you can keep the dialog window open and still continue working with other parts of Zeta Test. This is helpful when you e.g. want to display multiple information concurrently.